The best way to Build a Composition of Unit Charges

Como calcular custos unitários
If you’d like to understand how you can develop unit expense composition, you are going to just like the report you may read through under.

Here you’ll see a phase by phase to understand specifically how you can do that. So let us get ideal for the point.

Phase 1 for your Composition of Unit Charges: Get to understand the service

Among by far the most critical points should be to know and determine the identify in the solutions that will be carried out throughout the function, along with the whole unit of the execution.

go through much more right here: planilha orçamento de obra

For this, it’s essential to produce a very detailed description, through which it will be achievable to know the entire strategy as well as execution processes.

Being aware of the complete service for being performed, you may create The Composition of Unit Expenditures. So, let us head to stage two.

Phase 2: Determine the inputs

Maybe you feel this stage is extremely obvious. Even so, a lot of people do not know the way to recognize service inputs. But you will have to recognize just about every one particular with the time of execution.

Hence, we can identify three elements to be defined:

Material: Refers to all types of elements to be used in the course of all stages on the perform. For instance we have sand, stone, cement, steel bars, and so on.
Labor: All costs which have to do with hiring all kinds of specialized companies. Usually they’re masons, painters, servants, carpenters and some others.
Gear: this is the worth that is associated to the acquisition or rental of different gear or machinery required. Amongst them, sander, drills, trash, and so on. might be uncovered.
Stage three: Survey the input costs

In phase three, it really is required to develop the Composition of Unit Fees by raising direct prices related to your inputs. Such as, wages and labor fees along with the worth from the order of your materials.

Commonly it seems to be some thing like the illustration below

Labor costs (salary + costs): like a mason: R $ 19.81 per hour and Servant: R $ 14.01 per hour.
Expenditures of Elements, such as solid ceramic brick at R £ 0.31 per unit.
Stage four: Determine input consumption

Once you apply the unit price composition, it is possible to determine the full productivity of one’s workforce. On the other hand, in order to do this, it can be required to accompany the whole staff during the execution of your service.

Also, it’s essential to note the hours worked by every single from the contractors, provided the quantity of material for being used:

Following the instance of your checklist above, we’ve the data:

Labor Productivity: 1 Mason and 1Servente invested about 24 hrs to carry out 3 m³ of the services;
Resources yield: If 3,285 strong ceramic bricks of five x ten x 20 cm and 0,855 m³ of 1: 2: eight (cement, lime and medium sand) mortar had been employed to complete 3m³ from the services.
Step 5: Obtain the indexes

Possessing every one of the info at hand, we will determine each of the consumption indices of each input to run a service unit.
Step 6: Receive the unit rate on the services

Did you come across the consumption index of your inputs? If yes, quite effectively. Now you go to stage six to the composition of unit expenditures.

All you should do is multiply the input consumption index by your unit value to search out the total price of every.

That way, after adding up the total cost of every input, it is possible to get the entire unit value composition. So, you’ve presently reached your objective with this post, and now it is possible to use it.